P.030
EBRD — water pollution control in Qarun Lake
Fayoum, Egypt · 2020
EBRD provided a sovereign loan of up to EUR 186 million to Egypt, co-financed by up to EUR 172 million from the European Investment Bank and a EUR 30 million investment grant from the EU Neighbourhood Investment Facility, supporting the Bank's Green Economy Transition approach. Scope included ESIA studies for 25 facilities to EEAA guidelines for construction and operation permits, the same studies to EBRD guidelines as a requisite of the finance process, stakeholder engagement plans, and public consultations and hearings at site locations.
P.031
Qarun Lake — programme launch
Fayoum, Egypt · 2020
Programme meeting with the Fayoum authorities.
P.032
Qarun Lake — Phase 1 scope
Fayoum, Egypt · 2020
Delivered in two phases, with Phase 1 under this contract: construction of 4 new wastewater treatment plants, expansion of 7 existing plants, rehabilitation of 10, decommissioning of 6, expansion of the sewer network by approximately 2,350 km, construction of approximately 260 km of pressurised rising mains and around 100 new pumping stations, and procurement of 150 evacuation trucks.
P.033
Qarun Lake — design approach
Fayoum, Egypt · EBRD, HCWW, FWWC
Design of new and enhanced plants for FWWC addressed four drivers — public health, environmental protection, water conservation and whole-life-cycle cost — trading reduced OPEX and higher land area with simpler operation against high OPEX, reduced land area and complex operation.
P.034
Qarun Lake — design objectives
Fayoum, Egypt
The plants were set to maximise reliability and robustness, treatment and sludge process efficiency, reuse potential, flexibility of discharge, future adaptability and residuals such as power generation; and to minimise capital and operating cost, maintenance, power and chemical use, environmental impact, manning, odour and emissions.
P.035
Qarun Lake — process flow diagram
Fayoum, Egypt
Treatment train from inlet chamber, screens and grit removal through oxidation ditches and final sedimentation to the chlorination contact tank and flow meter, with activated and thickened sludge pumping, sludge thickener, drying beds and internal pumping station.
P.036
Qarun Lake — design deliverables
Fayoum, Egypt
Outputs spanned process flow diagrams, hydraulic profiles, geotechnical surveys, operating and process control philosophies, influent and effluent criteria, electrical drawings, process unit sizing, mechanical technical schedules, P&IDs, FDS, performance schedules, commissioning plan, site layout and pipe routes, and a pre-tender health and safety plan — with HAZOP attendance and action closure among the required tasks.
P.037
Qarun Lake — hydraulic modelling
Fayoum, Egypt
Network model and hydraulic profile through the works, tracking soffit, invert, water level and energy level across the drainage chain.
P.038
Egyptian Army National Services Projects — Arab Organization for Industrialization
Egypt · 2019
Planning, execution and completion of awarded projects to strict deadlines and budget, acquiring resources and coordinating team and third-party effort. Works included Marsa Matrouh STP (60,000 m³/day, EA process), Busilia El Sebia STP (27,000 m³/day, MBBR), Al Kalah Sharq STP (6,000 m³/day, MBBR), the Itssa 800 mm water supply pipeline, Al Balmoon STP (10,000 m³/day, MBBR), sanitary drainage projects at Al Monofia–Ashmoon, Al Gharabia–Al Salween, Al Behira–Kafr Al Dafwary, Aswan–Edfu and Al Mahala, and Siwa STP (10,000 m³/day, oxidation pond).
P.039
AOI projects — site team
Egypt · 2019
Site visit with the project team at one of the treatment works.